Amendments to Permitted Development (PD) Rights introduced in early April 2014 have transformed the landscape for anyone wishing to undertake a barn conversion in England (not applicable to the rest of the United Kingdom as it currently stands).

What has Changed?

As a result of the amendment, it will now be possible to convert existing agricultural buildings – barns for example – into homes without needing to expressly apply for planning permission, as had previously been the case.

Permitted Development Rights allow homeowners to carry out building work to their homes without needing to apply for planning permission from their local authority and have traditionally been used to enable minor extensions, loft conversions and the creation of outbuildings to be carried out without the need for notification.

What are the Details?

The Barn Conversion clause comes about as part of a new Class – MB – into Part 3 of the Second Schedule of the General Permitted Development Order. This new class authorises change of use of a building and any land within its curtilage from use as an agricultural building to a use falling within Class C3 – dwellings. It also authorises building operations ‘reasonably’ necessary to convert the building to residential use.

  • The site must have been used solely for agricultural use.
  • The barn must have existed on by 20th March 2013 (no building new barns!). New barns can be built and converted into homes but must exist as solely agricultural buildings for at least 10 years.
  • The total floorspace of your barn to be converted must be no more than 450m² – if the barn is bigger, you’ll only be able to convert to a maximum of 450m².
  • The 450m² can be divided into three separate dwellings.
  • If the site is subject to an agricultural tenancy, landowners must have the express consent of their tenants.

How Much Can You Rebuild?

Class MB permits reasonable building operations to convert a barn into a house, but only within the envelope of the existing structure. It permits partial demolition and rebuilding of the barn, but the extent of this allowance will probably be decided by case law.

Most experts believe it unlikely that flimsy Dutch barns or glasshouses could be simply knocked down and replaced with a new house (even if it were to mimic the appearance of the existing) although this is something that will be established as homeowners and local authorities dispute the detail.

However, significant improvement to the existing fabric, including new windows, even new walls as required, will be permitted under MB.

Are There any Exclusions?

Class MB – the barn conversion clause – doesn’t apply on any site within so-called Article 1(5) land, i.e. National Parks, Conservation Areas, etc.)

What do I Need to do Before I Convert my Barn?

As is increasingly the case with the more controversial elements of Permitted Development, Class MB is subject to what’s known as a Prior Notification procedure.

What is Prior Notification?

Prior notification came into force in 2013. Under this planning change, single-storey, rear residential extensions can be built up to 8m in depth (6m for a semi or terrace), provided that boundary neighbours are first informed or given ‘prior notification’.

As long as there are no objections, or any objections received have no planning merit, then a Certificate of Lawful Development is issued.

The 2013 changes also allowed for the change of use of buildings from office use (B1) to residential (C3).

Prior Notification Extended to Agricultural Buildings

In April 2014, the scope for prior notification was expanded to include Class Q. This allows for the change of use from agricultural buildings to ‘dwelling houses’, subject to certain conditions. In addition, the agricultural building must be capable of functioning as a dwelling house without serious structural changes (although some operations would be permitted).

An agricultural conversion can result in the creation of no more than three residential units, using up to a maximum of 450m3 of internal floorspace.

Before starting, the converter must apply to the local authority to establish whether they will need to receive prior approval (!) for:

  • transport
  • noise impact
  • contamination
  • flood risk
  • and ‘Whether the location or siting of the building makes it otherwise impractical or undesirable for the building to change from agricultural use to residential use.’

As you can see, this does give the local authority power to veto the development (although their decision must comply with the policies in the National Planning Policy Framework). In many ways, this makes the Prior Notification process within Permitted Development a planning application by another name.

It is still too early to gauge the impact of the Prior Notification clause; however, as barns are often in isolated rural areas, one can imagine the issues of sustainability being raised as a potential objection by local authorities.

Likewise, Prior Notification is also required for the local authority to decide whether they need to have prior approval on the design and external appearance of the building. Again, any decision must be met within the context of the NPPF, but it’s not too difficult to conclude that this is just another form of planning application. Under the Prior Notification procedure, the local authority does have the right to impose conditions on the development. 

Articles like this Comments
Comments
  • Gwendolyne white

    Hi , I have 6 acres of land with 5 stables which have been there for about 8 years ,So what chance have we got in which to turn the stables into a bungalow. it is not a green belt area the stables are wooden with a concrete base I was always led to believe that anything with a concrete base is classed as permanent Do hope you can help

  • Ian Raper

    @Gwendolyne white
    The Agricultural building needs to be within an Agricultural Unit and used solely for Agriculture on 20.03.2014.
    Horses/stabling are not agricultural, unless they are work horses for use on the Agricultural Unit.
    An Agricultural Unit has to be established as such, ie. history of a viable commercial, agricultural business.
    If your stabling is/was for domestic use horses then it would not fit the criteria.
    However, if the stabling was used on 20.03.2014 for a solely Agricultural use, then maybe they do.,,

  • George Komoneski

    Hi,

    Could you please clarify the following extract from the above article.

    The 450m² can be divided into three separate dwellings. There is no limit on the number of barns that you can convert (say if there are five barns of 400m² each).

    My understanding of the legislation is that the 450m2 refers to the total footprint permitted on each agricultural unit. ie. Farm holding.

    So there would be a limit to the number of buildings one could convert.

    Your thoughts please.
    Rgs,
    George

  • Anonymous

    Hi George
    You’re right. It is 450m2 in total meaning no more than 3 on one holding. Of course planning permission can be sought but you’re right that the PD limits apply to a total of 450m2. I have amended the article to clarify.
    Thanks.
    Jason

  • George Komoneski

    Thanks for the clarification Jason.

  • Julie Mclean

    I have an agricultural building which fits the criteria and is approx 200m2 and 14ft high. The ground level of our barn is higher than the houses surrounding it so can I dig down to create a second floor? Also I would like to alter the pitch or style of the roof, it is currently 12/3?

  • Post a comment