What follows is a trade-by-trade analysis and build up of costs for a very basic four bedroom house, together with a note of the factors that could serve to increase them. Finance costs are not included as these will certainly be peculiar to each individual. Some other costs, such as those for carpets and landscaping, are included in order to give a proper comparison with a fully finished home and in order to bring the self-build project into line with the specification that most developers now follow. VAT is not generally included, except where it is nonrecoverable and is, therefore, a direct cost.
PRELIMINARIES AND ENABLING WORKS
| Designer's fees (approx £2,500 +VAT) |
£2,937.50 |
| SAP calculations (£120 +VAT) |
£141.00 |
| Planning fees |
£265.00 |
| Building regulations fees |
£535.00 |
| Electricity supply |
£900.00 |
| Gas supply |
£678.00 |
| Water and sewage supply |
£1,170.00 |
| Warranty |
£1,500.00 |
| Site insurance |
£513.00 |
If an architect is used rather than a local designer then the costs for the drawings may rise to around £6,000 or more if site supervision is required. This would be mitigated by the fact that engineer’s fees and SAP calculations would be included.
Service charges can vary considerably depending on the distance the supply has to come and the terrain it has to cross.
GROUNDWORKS
| Site hut/storage 17 weeks @ £39.99 +VAT |
£798.80 |
| Toilets 17 weeks @ £27.99 +VAT |
£559.10 |
| 5 tons Type 1 @£20/ton |
£100.00 |
| Labour 1 day ganger + 1 @£180/day |
£180.00 |
| 1 day digger (hire only) @£189.04 +VAT |
£222.12 |
| 1 day ganger G + 1 @ £180/day |
£180.00 |
| Pegs |
£15.00 |
| Digger 3 days @ 189.04 +VAT |
£666.36 |
| 3.5 day labour G + 2 @ £260 |
£910.00 |
| Soil away 6 loads @ £180 +VAT |
£1,269.00 |
| Level pins |
£30.00 |
| 1 day labour G + 1 @ £180 |
£180.00 |
| 4 loads concrete £402.36/load |
£1,609.44 |
| Pump hire £285 +VAT |
£334.88 |
| 45m² blocks £7.50/m |
£337.50 |
| Block layers 45m² @ £12/m |
£540.00 |
| Mortar |
£18.00 |
| 2 rolls dpc |
£6.66 |
| 1 bundle wall tiles |
£43.60 |
| Drainage exit lintels |
£64.00 |
| Mixer hire 1 week @ £15 +VAT |
£17.63 |
| 70m² floor beams £11.55 |
£808.50 |
| Infill blocks 65m² @ £7.50/m² |
£487.50 |
| Cranked vents 18 @ £3.45 |
£62.10 |
| Labour: 2 days G + 2 @ £260 |
£520.00 |
| Digger hire 2 days |
£444.24 |
| Labour: 6 days G + 2 @ £260 |
£1,560.00 |
| 23x 6m pipe @ £12.24 |
£281.52 |
| 3 bags pea shingle £45 each |
£135.00 |
| 8x gullies £16.07 each |
£136.76 |
| Fittings |
£390.21 |
| 6 No. inspection chambers |
£305.76 |
It is in the ground that most cost overruns tend to occur. This costing is based on a trenchfill foundation. If a deep strip foundation is used instead then the concrete costs would shrink, but the foundation blockwork costs would increase. Trenchfill gets you out of the ground in just one day and avoids any problems with weather or unstable trenches.
Deeper foundations cost more depending on the amount of spoil and concrete. Unstable ground might mean changing to a piled or raft foundation with add-on costs of between £4,000 and £8,000. Some groundworkers lay foundation blocks, others leave it to the bricklayers.
A solid concrete oversite could save £500 to £800, but beam and block floors provide a finite cost more acceptable to warranty providers.
BRICK AND BLOCKWORK/SUPERSTRUCTURE
| 12.283 bricks £260 per 1000 |
£3,193.58 |
| Labour 11,184 bricks @ £450/1000 including frame fixing, lintel bedding and insulation |
£5,032.80 |
| 190/m² insulating blocks @ £8.80 |
£1,672.00 |
| 120/m² concrete blocks @ £750 |
£900.00 |
| Blockwork labour @ £12/m |
£3,264.00 |
| Mortar |
£324.00 |
| External lintels |
£428.00 |
| Internal lintels |
£236.00 |
| Cavity insulation 160m² @ £3.83 |
£612.80 |
| 2 bundles wall tiles |
£87.20 |
| Retaining discs |
£27.57 |
| 2 rolls dpc |
£6.66 |
| 10 weeks mixer hire |
£176.30 |
| Skip |
£141.00 |
| 70m² beams @ £11.55 |
£808.50 |
| 65m² infill blocks @ £7.50 |
£487.50 |
| Batten clips |
£52.50 |
| Labour: Ganger + 2 @ £260 |
£520.00 |
| Crane hire |
£341.25 |
| PVCu supply |
£4,000.00 |
| Fitting |
£500.00 |
| 12 weeks hire £245.58 per week |
£946.96 |
Changes to a more expensive brick will affect the material costs but are unlikely to affect the labour or ancillary costs. Changes to a natural stone façade is likely to add considerably to the cost with the requirement for a backing block plus the extra cost of the stone. The labour is also likely to shoot through the roof as this is an expensive and increasingly rare skill and, taken together with the extra materials, you could be looking at between £7,000 and £10,000 extra. Changing to rendered blockwork might seem a cheaper option but in fact, because it involves two more trades – the plasterer and the decorator – and it also means that the scaffolding has to stay up longer, it could add £5 per square metre or close on £1,000. A timber first floor can save around £1,100. The decking and insulation is also around £600 cheaper than the insulated screed floor. Some bricklayers will undertake the beam and block first floor; others will prefer it to be done by the groundworkers coming back. PVCu windows are usually supplied and retrofitted by others. Timber joinery is fitted by the bricklayers as they go.
CARPENTRY
| 19 roof trusses @ £40 each |
£760.00 |
| Wallplate 22m @ £2.38 |
£52.36 |
| Plate straps |
£87.41 |
| Fascia 22m @ £5.10 |
£112.20 |
| Soffits 20m @ £6.93 |
£138.60 |
| Nails and fixings |
£48.69 |
| Bindings and bracings 150m @ 70p |
£105.00 |
| Labour: 5 days carpenter + 2 @ £300 |
£1,500.00 |
| Internal door lings 14 @ £14.32 each |
£200.48 |
| Staircase flight |
£429.42 |
| Newel post and base |
£215.48 |
| Window boards 12m |
£43.00 |
| Pipe boxing and odds |
£100.00 |
| Loft hatch |
£48.05 |
| Labour: 5 days carpenter @ £160 |
£800.00 |
| 14 doors @ £28.34 each |
£395.36 |
| Furniture and fixings |
£145.41 |
| Skirting 162m @ £1.80 |
£291.60 |
| Architrave 140m @ £1.56 |
£218.40 |
| Balustrading, handrails etc. |
£420.35 |
| Second fix labour: 8 days carpenter @ £160 |
£1,280.00 |
| Kitchen units purchase approx |
£3,500.00 |
| Kitchen fitting, approx 5 days @ 3160 |
£800.00 |
For between £1,500 and £2,000 the trusses could be changed to attic trusses, which would then allow occupation of the roof at a later date. Of all the elective extras, this is perhaps the most cost-effective. Internal doors, kitchen units and joinery can cost considerably more but may not actually add value to the home.
PLUMBING AND CENTRAL HEATING
| Pipe, fittings and wastes |
£852.78 |
| Labour: 6 days @ £200 |
£1,200.00 |
| 13 radiators + TRVs |
£796.25 |
| Boiler (gas condensing) |
£892.53 |
| Mains pressure gas cylinder |
£627.00 |
| Controls |
£200.00 |
| Labour: 9 days @ £200 |
£1,800.00 |
| Guttering 4x 6m @ £18.06 each |
£72.24 |
| Brackets 14 @ 87p |
£12.18 |
| Outlets 2 @ £4.12 |
£8.24 |
| Stop ends 4 @ £1.65 |
£6.60 |
| Downpipe 2 x 6m @ £16.08 |
£32.16 |
| Downpipe brackets 12 @ £1.86 |
£22.32 |
| Swan necks 4 @ £2.35 |
£9.40 |
| Rawl plugs and screws |
£14.81 |
| Labour: 2 days @ £200 |
£400.00 |
Underfloor central heating could add around £1,600 to the initial outlay but running costs might be much better as condensing boilers work more efficiently at the lower temperatures that are required.
Most modern houses now have a mains pressure hot water system either using a standard boiler or a combi system. You can spend considerably more on sanitaryware but it might not be cost-effective as the ‘wow factor’ in bathrooms is often achieved with the accoutrements and accessories.
Rainwater goods are usually fixed by the plumber but can be carried out by another competent tradesperson. PVCu sections are undoubtedly the cheapest. The soakaways and their connecting drains are carried out by the groundworkers.
ROOFING
| Undercloak |
£36.00 |
| Breathable underlay 3 rolls @ £135.37 |
£406.11 |
| Battens 484m @ 25p/m |
£121.00 |
| Nails and clouts |
£280.78 |
| Roof tiles, including 1,012 tiles, 74 eaves, 80 top tiles, 30 l/h verge @ £2.08 each |
£2,550.08 |
| 25 ridge tiles @ £2.41 each |
£60.25 |
| Mortar and colouring |
£25.00 |
| Mechanical conveyor |
£88.13 |
| Labour: 7 days roofer + 1 @ £220 |
£1,540.00 |
Handmade plain clay tiles in lieu of concrete interlocking, as costed, might add around £10,000. Even machine-made clay tiles would add about £4,000 and natural slates would add around the same. Breathable underlays might seem much more expensive than normal roofing felt but do not need additional ventilation to the roof void.
ELECTRICAL
| Cable, channel, sheathing, back boxes etc. |
£242.00 |
| Labour: 5 days @ £165 |
£825.00 |
| Faceplates, fans, consumer unit, pendants etc. |
£612.70 |
| TV aerials (s&f) |
£200.00 |
| Light fittings approx |
£300.00 |
| Labour: 5 days @ £165 |
£825.00 |
It is all too easy to go over the top with this trade, doubling or even trebling the price. Think very carefully about your needs. Mark up the plan and then mark the walls before the tradesperson starts. It is usual for the self-builder’s light fittings to be fitted by the electrician.
PLASTERING & INSULATION
| 55 sheets ceiling plasterboard @ £5.29 each |
£290.95 |
| Ceiling battens 150m @ 25p |
£37.50 |
| Tack ceilings: 2.5 days @ £220 |
£550.00 |
| Skin-coat ceilings: 2.5 days @ £220 |
£550.00 |
| Ceiling ancillary materials |
£138.01 |
| 14 pack insulation |
£341.88 |
| Labour: 2 days @ £90 |
£180.00 |
| Dry-lining 135 sheets plasterboard @ £5.29 each |
£714.15 |
| Walling adhesive |
£228.92 |
| Dry lining: 3 days @ £220 |
£660.00 |
| Skin-coat walling materials |
£278.97 |
| Skin-coat labour: 6 days @ £220 |
£1,320.00 |
| Skip |
£141.00 |
| Flooring insulation 140m² @ £5.36 |
£750.40 |
| Membrane |
£78.00 |
| Ready-mix screed 20 tons @ £49.95 |
£999.00 |
| Hoist |
£88.13 |
| Labour: 5 days @ £220 |
£1,100.00 |
Plasterers can be supply and fix or labour only. Hard plastering costs roughly the same as dry-lining but takes considerably longer to dry out sufficiently for it to be decorated. With dry-lining, one is also less likely to experience cracking. Coving can add between £500 and £900 but is rapidly going out of style in favour of cleaner lines.
A plasterer might want a conveyor or hoist brought in for first floor screed, adding around £88. The insulation to a cold roof void can only be put up once the ceiling is tacked. It can be done by plasterers but is usually left to less skilled labour. Plasterers might not always want to lay the membrane and underfloor insulation.
CERAMIC TILER
| 30m² tiles @ £16 |
£480.00 |
| Adhesive, grout and additives |
£372.72 |
| Labour @ £20m² |
£600.00 |
| 23m² tiles @ £11 |
£253.00 |
| Adhesive, grout and spacers |
£127.49 |
| Labour @ £15m² |
£345.00 |
Once again, this trade is often taken on by the self-builder. Professionals do, however, do it much quicker and much more neatly.
EXTERNAL WORKS
| Tarmac driveway 40m² @ £20 (s&f) |
£800.00 |
| 30 panels @ £15/post (s&f) |
£465.00 |
| Slabs 130 No. @ £2.50 |
£325.00 |
| Ballast - 2 ton |
£40.00 |
| Cement: 10 bags @ £2.83 |
£28.30 |
| Labour: 4 days @ £180 |
£720.00 |
| Mixer hire 1 week |
£17.63 |
| Turf 300m² |
£507.00 |
| Labour: 2 days @ £180.00 |
£360.00 |
Savings can be made by swapping to a pea shingle driveway at around half the cost. Retaining walls can be very expensive. Keep all topsoil on site and as much subsoil as you need to make up levels. Remember, stacked soil shrinks to under half its volume. Sending soil away is expensive — buying it back is even more expensive!
DECORATION
| 72 litres trade emulsion |
£190.08 |
| 10 litres undercoat |
£47.10 |
| 10 litres satinwood |
£61.30 |
| Fillers, solvents and cleaners |
£50.91 |
| Brushes, sandpaper etc. |
£25.55 |
| 14 days labour @ £110 |
£1,540.00 |
This trade is often undertaken by the selfbuilder. However, the decorator is also responsible for ‘snagging’ many of the problems left by other trades and the maxim ‘prior preparation prevents poor performance’ are certainly the watchwords. It is one of the cheapest in terms of labour costs and day rates.
CARPETS
| 110m² @ £10.50 (s&f) |
£1,155.00 |
It has become the norm for developers to put in carpets and, therefore, to be properly finished, a self-build home should also include these costs. Carpet can vary from £7.50 per square metre up to £40 and even beyond.
GRAND TOTAL
| TOTAL |
£92,679.16 |
| + 10% contingency |
£9,267.92 |
| REVISED TOTAL |
£101,947.08 |
| Cost per m² |
£728.19 |
Further reading:
